Ongoing Construction Work Status

Undergoing Civil/Electrical infrastructure works during the year 2020-21 and 2021-22                                      

33/.433 KV Electrical Substation

IASST requested APDCL for up gradation of feeder power supply of IASST substation from 11 kV to 33 kV. Based on their communication, APDCL agreed to install a 33 kV Substation (SS) at IASST premises with a 33 kV dedicated transmission line from Garchuk SS. APDCL informed about the sanction of 33 kV dedicated line to the Sub-station at IASST .An MOU was signed between IASST and APDCL to set-up 33/11 kV SS at the IASST premise and agreed to keep provision for a 33 kV bay for use of the institute in the proposed 33/.433 SS at IASST. The following works related to construction of 33/.433 Substation at IASST are done/ under progress

  1. Supply, installation& Commissioning of LV Panels for 33/.433 KV IASST Substation:The work was allotted to M/S North eastern Engineers, Guwahati at a work value of Rs 57,85,515/-. The work is in progress.
  2. Supply, installation and commissioning of two nos. of 33/0.433KV 1600KVA Oil filled Transformer for 33/.433 KV IASST Substation:The work was allotted to M/S North eastern Engineers, Guwahati at a work value of Rs 50,60,000/-. The work is in progress.
  3. Installation and commissioning of 33/.433 KV substation of IASST: The work was allotted to M/S North eastern Engineers, Guwahati at a work value of Rs 59,51,552/-. The work is in progress.
  4. Construction of 33KV line, 11 KV&LT composite from 33/11kv Garchuk substation to proposed 33/11 kv substation at IASST campus(Line length 5.2 km)The work was done by Assam Power Distribution Corporation Ltd(APDCL) at a cost of Rs1,23,17,334. The work is complete.