1 | Central Instrumentation Facility & Drug Development Centre | M/s Bhaskar Baruah,Guwahati,Assam | 140000000 | Work is provisionally completed on 16.10.19 & final checking under progress. For testing of A.C & Electrical part wait for power supply., Extra work- partition work under progress. |
2 | Animal House Facility Building | M/s Navrup India | 12300000 | Work is provisionally completed & final checking under progress. For testing of Mechanical part wait for power supply. |
3 | ST/SC Training Facility | M/s Elemente Designers Homes | 16457400 | Work completed , final bill already paid. Balance only extra item bills. |
4 | Construction of Academic Staff Quarter | M/s Bimal Kumar Agarwalla | 71300000 | 90% work completed. Remaining works includes – electrical fittings,sanitary fittings,windows fitting,internal road,final coat painting and cleaning under progress. Expected date of completion 31.03.2020. |
5 | Observatory Building | M/s Bimal Kumar Agarwalla | 7000000 | Main order work completed.Extra work on progress. |