Ongoing Construction Work Status

Undergoing Civil infrastructure works during the year 2025-26

Sl No.Name of Work
Agency
Estimated Amount
Tender Amount
Agreement No
Schedule DOS
Schedule DOC
Expected DOC
Total upto dated payment
Remark
1Construction of Girls Hostel Building, Pump House including IEI fans & fitting and E& M Services for IASSTCPWD (M/s Laxman Sharma)₹ 20,99,70,784.00₹ 15,25,83,942.00Agreement No. 20/CE/EE/GD/2022-2305.03.202304.03.2025Work Completed1795.39 lakhphysical progress :100.0%, process started for for handing over taking over
2Construction of Girls Hostel Building RCC Overhead tank capacity of 100 KLO and filtration plant and pump house and furntiure for IASST SH Construction of Parking Shed Covering of Courtyard by tensile fabric shed over composite flexible structure ,Installation of 2(two) nosfiltration plant and 1No. Deep tubewellCPWD (M/s D.S. Trading)₹ 2,62,83,203.00₹ 1,53,49,391.001/CE/EE/GD/2025-2613.04.202512.08.2025Work CompletedDoDo
3Construction of Girls Hostel Building, Pump House including IEI fans & fitting and E& M Services for IASST SH Providing and installation of furniture Modular kitchen and commercial kitchen equipmentCPWD (M/s Shivam Trading & Co,)₹ 1,23,85,225.00₹ 94,12,771.008/EEGD/2025-2608.07.202507.09.2025Work CompletedDoDo
4Raising of existing boundary wall and providing Concertina Coil Fencing around IASST (Institute of Advanced Study in Science and Technology) Campus at Paschim Boragaon ,Garchuk ,Ghy-35CPWD (Mr.Hemanta Bhuyan)₹ 82,95,826.00₹ 49,94,087.0037/EE/GD/2024-2519.03.202516.07.202505.11.2025NApysical progress 80.0%
5Construction of L Shape Foot Bridge Connecting Administrative Cum Academic Building & SAIF Building at First Floor level at IASST (Institute of Advanced Study in Science and Technology) Campus at Paschim Boragaon, Garchuk, Ghy-35.CPWD (Mr. Nripen Kalita)₹ 76,32,469.00₹ 51,50,161.004/EE/GD/2025-2621.06.202518.09.202530.11.202538.36 lakhphysical progress 90.0%